NCC Command Center / Dashboard

Total BOQ Value

₹68,39,180.00

BOQ Distribution

1.1.01... ₹1k
1.2.05... ₹56k
Brickwork in Super... ₹130k
Excavation... ₹1,500k
Excavation in all ... ₹4k
M25 Concrete... ₹3,696k
PCC for Foundation... ₹223k
Plywood Formwork f... ₹20k

Scheduled Value

₹8,41,260.00

Overall Progress

35.7%

Labor Requirement

142 MD

Trade Matrix

HELPER 71
STEEL FIXER 66
CARPENTER 3
MASON 2

Project ERP Command

Real-time resource demand and schedule tracking enabled for Sector 43 Infrastructure.

BOQ Master Registry

Grand Total ₹68,39,180.00
Item & CodeQtyTotal INR
#Excavation in all types of soil 14.0 Cum ₹3,500.00
#PCC for Foundation 46.0 Cum ₹2,23,100.00
#RCC for Footing 23.0 Cum ₹1,28,800.00
#RCC for Columns 14.0 Cum ₹89,600.00
#TMT Reinforcement Steel 16.0 MT ₹9,92,000.00
#Plywood Formwork for Beams 41.0 Sqm ₹19,680.00
#Brickwork in Superstructure 25.0 Cum ₹1,30,000.00
#1.1.01 250.0 Cum ₹500.00
#1.2.05 5,600.0 Cum ₹56,000.00
#1.1.01Excavation 1,500.0 Cum ₹3,75,000.00
#1.1.01Excavation 1,500.0 Cum ₹3,75,000.00
#1.1.01Excavation 1,500.0 Cum ₹3,75,000.00
#1.1.01Excavation 1,500.0 Cum ₹3,75,000.00
#1.2.05M25 Concrete 300.0 Cum ₹16,80,000.00
#1.2.05M25 Concrete 30.0 Cum ₹1,68,000.00
#1.2.05M25 Concrete 300.0 Cum ₹16,80,000.00
#1.2.05M25 Concrete 30.0 Cum ₹1,68,000.00

Labor Demand Matrix

Total Requirement 142 Man-Days
HE
HELPER
71 Headcount Required
ST
STEEL FIXER
66 Headcount Required
CA
CARPENTER
3 Headcount Required
MA
MASON
2 Headcount Required